Advising a Contractor on a Master Services Agreement for Façade Restoration of a London Office
The Project
We advised a specialist construction contractor in connection with a substantial façade restoration project involving a commercial building in London.
The project involved extensive external restoration and associated works to the building's façade. Given the nature and location of the property, and the fact that it remained occupied throughout the works, the project required careful consideration of the contractual, technical and operational risks affecting the contractor.

The Challenge
The contractor was required to enter into a detailed Master Services Agreement (MSA) governing its appointment and the performance of the works, together with a detailed Specification of Works.
A key concern was ensuring that the two documents worked together and accurately reflected the scope of the contractor's obligations. It was important that the contractor did not inadvertently assume responsibility for matters outside its control or accept obligations for works, conditions or risks that had not been identified or properly priced.
The occupied nature of the property also created additional considerations concerning access, security, health and safety, working hours, disruption and coordination with the building's occupier.
Our Advice
We carried out a detailed review of the proposed Master Services Agreement and Specification of Works and advised the contractor on their legal and commercial implications.
Our advice included consideration of:
the precise scope of the contractor's obligations;
the relationship and order of precedence between the MSA and Specification of Works;
responsibility for design and specification;
site conditions and unforeseen circumstances;
variations and additional works;
programme and completion obligations;
extensions of time and delay;
access to the building and restrictions imposed by the occupier;
health and safety and site management responsibilities;
protection of the existing façade and other parts of the building;
defects and remedial obligations;
payment provisions and valuation of additional works;
insurance and allocation of risk;
indemnities and limitations of liability; and
termination and the consequences of termination.
Master Services Agreement and Specification
A particular focus of our advice was the interaction between the MSA and the Specification of Works.
Where a contract comprises several documents, inconsistencies between them can create uncertainty and potentially lead to disputes about the contractor's obligations.
We therefore advised on the contractual hierarchy and the wording required to establish which document would take precedence if an inconsistency arose.
We also reviewed the Specification from the contractor's perspective, identifying provisions which could create uncertainty regarding the extent of the works, responsibility for unforeseen conditions or the requirement to undertake additional work without an appropriate adjustment to the contract price or programme.
Our objective was to ensure that the contractual documentation reflected the commercial deal that the contractor had actually agreed.
Managing an Occupied Building
The fact that the building was occupied was an important consideration.
The contractor needed to be able to carry out the restoration works while accommodating the requirements of an operating professional business.
We advised on provisions dealing with access, working arrangements, coordination with the occupier and other contractors, site restrictions and potential disruption.
These matters can have a direct impact on programme and cost. We therefore sought to ensure that the contractor was not exposed to unlimited liability for delays or additional costs resulting from restrictions or requirements imposed by the client or occupier.
The Outcome
Our advice enabled the contractor to enter into the Master Services Agreement with a much clearer understanding of its contractual obligations and the risks associated with the project.
The contractual documentation was reviewed and negotiated from the contractor's perspective, with particular attention given to ensuring that the MSA and Specification of Works worked together and accurately reflected the intended scope of the project.
The contractor was therefore better positioned to manage its commercial and contractual exposure while proceeding with the restoration works.
Why This Matters
Construction contracts are often made up of several documents, including a Master Services Agreement, specifications, schedules, drawings, pricing documents and project-specific requirements.
It is not enough for each document to look reasonable in isolation. They must work together.
An unclear scope of works or poorly drafted specification can expose a contractor to claims for additional work, delay, defects or costs that were not properly anticipated when the contract was priced.
This case demonstrates the value of obtaining construction-law advice before signing the contract, rather than waiting until a dispute arises.
We help contractors identify contractual risks at the outset, negotiate appropriate risk allocation and ensure that the contractual documentation properly reflects the work they have agreed to undertake.
For contractors undertaking refurbishment, restoration or façade works on occupied commercial properties, early advice can be particularly important where access restrictions, working hours, unforeseen conditions, programme requirements and third-party occupier requirements can materially affect the cost and delivery of the project